Project Status Cost Summary
Use the Project Status Cost Summary report to monitor the cost status of the projects for an organization or set of organizations by comparing estimate-at-completion (EAC) cost amounts, as of the current fiscal period, to total baseline budget cost amounts.
For each project, the report displays the following:
-
Inception-to-date (ITD) actual burdened cost through the period preceding the current period in Costpoint Planning
-
Estimate-to-complete (ETC) burdened cost
-
Forecast burdened cost (ITD actual burdened cost + ETC burdened cost)
-
Total baseline budget burdened cost
-
Variance between forecast cost and baseline budget cost (Total baseline budget burdened cost – Forecast burdened cost)
-
Variance percentage (Variance / Total baseline budget burdened cost)
To call your attention to potential issues, the report highlights negative or positive variances greater than $25,000 and variance percentages of 5 percent or more.
- Related Topics:
- Options
You can select options on how you want the report to be displayed. - Reconcile Project Status Cost Summary
Use the Costpoint Planning reports to reconcile data on the Project Status Cost Summary report. - Prompts
Use the prompts to run the Project Status Cost Summary report. - Sample Report
This is a sample of the Project Status Cost Summary report.