Contents of the Update Project Progress % Screen

Use this screen to update Project Progress %, the result displayed will only be final version Project Budgets and not EAC’s.

Contents

Field Description
Project

Select All, One, or Range from the drop-down menu. When you select All, all budget level, final version project budgets will populate the result set.

Last Closed Period

This field defaults to last closed period end date and is not editable.

Project Progress % Details

The following information is displayed in the Project Progress % Details grid.

Column Headings Description
Project ID This column displays the Project ID.
Project Name This column displays the name of the project.
Version This column displays the budget version number.
Version Code This column displays the version code if one has been set up in the budget.
Budget Status This column displays the status of the budget if Incomplete, Complete or Approved.
Previous Progress % This column displays the percentage of previous progress.
Previous Progress FY/PD This column displays the previous progress fiscal year/period date.
Current Progress % Use this field to enter the percentage for a certain project budget or budgets which you need to process or create a report. Once you save the % it updates the percentage progress for the Previous Progress % column.