Contents of the Update Project Progress % Screen
Use this screen to update Project Progress %, the result displayed will only be final version Project Budgets and not EAC’s.
Contents
Field | Description |
---|---|
Project |
Select All, One, or Range from the drop-down menu. When you select All, all budget level, final version project budgets will populate the result set. |
Last Closed Period |
This field defaults to last closed period end date and is not editable. |
Project Progress % Details
The following information is displayed in the Project Progress % Details grid.
Column Headings | Description |
---|---|
Project ID | This column displays the Project ID. |
Project Name | This column displays the name of the project. |
Version | This column displays the budget version number. |
Version Code | This column displays the version code if one has been set up in the budget. |
Budget Status | This column displays the status of the budget if Incomplete, Complete or Approved. |
Previous Progress % | This column displays the percentage of previous progress. |
Previous Progress FY/PD | This column displays the previous progress fiscal year/period date. |
Current Progress % | Use this field to enter the percentage for a certain project budget or budgets which you need to process or create a report. Once you save the % it updates the percentage progress for the Previous Progress % column. |
- Related Topics:
- How to Update Project Progress
Use this procedure to update project process.