If a project is subject to the allocation of ACRN or ACRN/Line Item amounts to specific resources such as Direct Labor or Other Direct Costs, use this subtask to link the general ledger account(s) to the ACRN or ACRN/Line Item. 
  
 
	  
		This subtask is required if the 
		  Billing Requirement is 
		  ACRN Only w/ Mapping or 
		  ACRN/Line Item w/ Mapping.  
		
 
		Complete this subtask after you have added the ACRN or ACRN/Line Item data in the Project ACRN Details table window. 
		
 
		Additional maintenance on this screen is required only if a new account or account range is needed. 
		
 
		Note: You can enter data for a given ACRN or ACRN/Line Item in only one subtask, Accounts or PLC Mapping. If you manually upload data into both subtasks for an ACRN or ACRN/Line Item, the data on the PLC Mapping subtask is used and the data in the Accounts subtask is ignored. 
		
 
	 
 
	 Contents
 
		 
		| Field | Description | 
|---|
 
		   
			 | Starting Account | Enter, or click 
				   to select, the first account in the range of accounts that you want to use this ACRN or ACRN/Line Item. Account ranges cannot overlap. You can enter project-required, detail accounts in this subtask, or summary accounts. This field is required. | 
 
		   
			 | Ending Account | Enter, or click 
				   to select, the last account in the range of accounts that you want to use this ACRN or ACRN/Line Item. Account ranges cannot overlap. You can enter project-required, detail accounts in this subtask, or summary accounts. This field is required. |